Sales promised a big customer delivery in ten days. Production learns about it in the morning meeting, the line is busy, and a key material will not arrive for two weeks because nobody ordered it. Then come emergency decisions: bumping another order, buying at a premium, overtime and an unhappy customer.
That is the absence of production planning. This article walks from the master schedule to work and purchase orders.
Three questions
- What to make and when, from orders and forecasts.
- Which materials and when, from BOMs, stock and lead times.
- Is there enough capacity, from workstations, operation times and shifts.
Master production schedule
The MPS sets quantities of finished goods per period from firm demand (sales orders) and forecast demand. ERPNext 16 includes a master production schedule combining sales orders and forecasts.
| Strategy | Demand source | Note |
|---|---|---|
| Make to stock | Forecasts and reorder levels | Standard products |
| Make to order | Firm orders | Customer specs |
| Assemble to order | Orders plus component stock | Fast assembly |
| Mixed | Both | Most common |
Material requirements planning
Net requirement = gross requirement − available stock − expected receipts + safety stock
ERPNext's Production Plan pulls sales orders or material requests, explodes multi-level BOMs, considers stock in chosen warehouses and proposes work orders and material requests dated to need. Record lead times per item so imported materials are ordered early enough; see critical raw materials.
Capacity
Summing planned operation times per workstation per period reveals bottlenecks before they happen. ERPNext supports capacity planning for workstations when creating work orders with job cards.
From plan to execution
- Work orders from the plan.
- Job cards per operation with actual time and quantity.
- Material requests to RFQs, purchase orders or transfers.
- Material transfer to work in progress.
- Manufacture entry with consumption and cost.
Planning is a cycle
Plans change daily. Run a fixed cycle, often weekly, with a short frozen period where orders change only by decision, and route urgent changes through clear controls.
Safety stock and reorder points
Too much safety stock locks cash; too little stops the line. Size it by demand variability, lead time and supplier reliability.
| Material | Lead time | Suppliers | Safety stock |
|---|---|---|---|
| Local, common | Short | Many | Low |
| Local, specialised | Medium | Few | Medium |
| Imported | Long | Few or one | Higher, closely watched |
Reorder point = consumption during lead time + safety stock. ERPNext reorder levels per item and warehouse create material requests automatically; see inventory and cash flow.
Subcontracted stages
Printing, coating or heat treatment at a supplier must be in the plan with its lead time. ERPNext subcontracting orders track materials sent and received.
A shared language with sales
When sales see available capacity and materials before promising dates, and planners see sales forecasts, the plan becomes shared.
Planning KPIs and getting started
| KPI | Reveals |
|---|---|
| On-time delivery | Plan quality |
| Work orders on time | Execution |
| Line stops for materials | Material planning |
| Workstation load | Bottlenecks |
| Changes in frozen period | Discipline |
- Fix BOM and stock accuracy first.
- Record lead times and safety stock.
- Define workstations and operation times.
- Start a weekly cycle for a product group.
- Expand once stable.
Frequently asked questions
MPS vs MRP?
MPS decides finished goods and timing; MRP calculates materials and when to order them.
Does ERPNext support MRP?
Yes, through the Production Plan; version 16 adds a master production schedule.
How to avoid line stops for materials?
Lead times, safety stock and a regular planning cycle.
How often should the plan be updated?
On a fixed cycle, usually weekly, with a short frozen period.